Case Studies
Services & Workshops
Promec Enginnering Workshops:
8000 Sq. Ft. Fabrication Facility
6 Tonne single lift Gantry Crane
Calibrated Machinery
Local Exhaust Ventilation
Capacity to form, roll and sheet cut steels & pipe sections
2 Double doors Full Height Goods In / Out
Controlled Electrode & Consumable Stores
Services
Civil Engineering
Deep excavations
Confined space working
Ground surveys
General groundworks
Mechanical Engineering
Coded welding
Pressure testing
General fabrication
Cathodic Protection
Surveying
Design
Installation
E & I Services
In partnership with our approved E&I company
Design, Drawings & Surveys
Blasting, Painting & Coatings
CDM Principal Contractor Role
Project Management
Sectors
Gas
National Grid
Northern Gas Neworks
Cadent
Wales & West
Oil
Bristish Pipelines Agnecy
Oil Pipelines Agency
CLH
Exxon Mobil
Water
Thames water
Bristol water
Wessex water
Power
SPL
EDF
Exxon Mobil - Pipe Diversion – 1 kilometer of 150NS / 200NS Pipe
Key Facts:
Diversion of existing pipework to allow new roads and infastructure.
Field Fabrication, Welding and Testing of a Carbon Steel line carrying Hydrocarbons.
Duration: 19 Weeks
Location: Bristol
Fence erected adjacent to reen and spread prepared
Pipe supports and
route marked out
Pipe strung and
positioned
Field fabrication and welding
Welding shelter and forced air
Trench Prepared
Lower & lay of pipeline
Lower & lay of pipeline
Northern Gas Networks – HP, MP & LP 450/500mm Gas Diversion
Key Facts:
Diversion of HP, MP & LP Steel & PE Lines
Duration: 42 Weeks
Location: Newcastle
Existing steel & PE
pipes exposed
New & existing routes of pipework
New PE and steel pipe
installation
Welding shelter &
forced air
Existing line identified
Lower and lay of pipeline
New installation of PE and steel 450/500mm lines
Embankment works
Squeeze off connections
Area backfilled and
reinstatement
Northern Gas Networks – Saltwick AGI, Mechanical, Civil, E&I Upgrade
Key Facts:
Site meter stream, Mech, Civil & E&I Upgrade
Duration: 37 Weeks
Location: Saltwick
Preparation for new cable ducts and draw boxes
New kiosk base slab –
Rebar and shuttering
Wind & water line preparation
Excavation, P9 works & preparation for Hot Tap procedure
New bypass pipework, installed
in preparation to be buried & backfilled.
Complete with new support &
concrete pads.
Existing pipework blasted & painted with new flange protectors
Cable duct draw pits with new covers
Wind & water lines completed, new surrounds and backfilled
British Pipeline Agency – New UK Central Operations Control Centre
Key Facts:
New Retaining Wall, Electrical Ducts and Slab for UK Control Centre
Duration 24 Weeks
Location - Kingsbury
View prior to construction work
Commencement of excavations
Completion of phase 1 excavation
Commencement of retaining wall build
Installation of cable duct
Retaining wall complete
Re-bar installation
Concrete pour works
Completion of pour
Buidling sited and new security fencing installed.
Rear view of retaining wall with new handrails positioned on top blocks. Back filled with stone and chippings.
Oil Pipelines Agency- Tank Feed Pipework
Key Facts:
Site survey to measure and produce drawings to fabricate, test and installation of new feed and return pipework for JetA1 fuel hydrocarbons.
Existing pipework was removed and transported off site during a planned outage.
Valves, NRV’s and new site glass systems were installed with volume detection.
Duration: 7 Weeks
Location: Hallen
New concrete bases were set within the side of the embankment to allow for the new pipe sections to be installed.
New pipework had to run adjacent to the steps. These were supported on each section with a bespoke fabricated bracket.
Final fire prior to paint touch up.
SPL – 1,140 MW Gas-Fired Power Station - Module Link Bridge – Design & Build
Key Facts:
Requirement for a link bridge between two modules
Duration: 8 weeks from design to completion
Location: Bristol
Area with no link bridge or access
New link bridge & access
During Construction
During Construction
Installation Complete
Installation Complete
New access ladder with landing & safety gate
Access landing &
gate No 1
Access landing &
gate No 2